image description
School Building Needs Commission gets an update on the $3 million Pittsfield High boiler projecton Tuesday.

Pittsfield High Boiler Replacement Underway

By Brittany PolitoiBerkshires Staff
Print Story | Email Story

PITTSFIELD, Mass. — Pittsfield High School's boiler project is underway and the school will have heating upgrades for the winter season. The effort will replace three inefficient, original-to-the-building boilers that are past their useful life.

"That school is going to operate a whole lot different," Building Maintenance Director Brian Filiault told the School Building Needs Commission on Tuesday.

"There's not going to be fluctuations in there anymore."

A temporary boiler arrived at the school last week and will be connected to the building in the coming weeks. The replacement boilers arrive next week and will go online in December.

The project, originally set to be paid by American Rescue Plan Act monies, is expected to total about $2.8 million.

In June, the City Council authorized the borrowing of $3 million to replace the school's nearly 100-year-old boilers. After looking at the numbers, it was clear that the allocated $1 million in ARPA funds would not be enough.

The boilers original to the building were converted locomotive engines that were extremely inefficient and expensive to maintain. One boiler was non-operational and another was severely compromised.

A failure during the heating season means that the school would have to close.

Everything in the boiler room has been removed, including the former locomotives. Filiault said it is a completely different space.


"It's a major undertaking," he said. "That project is very intense, there's been a lot of work done to get us to this point."

Work has been formerly done to calm irregularities in the school's climate. The old pneumatic heating system was uncontrollable and is being converted to a digital system that could be controlled from Filiault's office.

He sees the new boilers as the workhorses of the system.

With a pending application to the Massachusetts School Building Authority for a combined build on the site of Crosby Elementary School, the commission will likely not meet again until next year.

The proposal rebuilds Conte Community School and Crosby on the West Street site with shared facilities, as both have outdated campuses, insufficient layouts, and need significant repair. A rough timeline shows a feasibility study in 2026 with design and construction ranging from 2027 to 2028.

In late August, MSBA conducted a senior study visit to the schools. Superintendent Joseph Curtis reported that they asked a series of questions, such as the district's commitment to the project facility, and were impressed by the Pittsfield Public Schools Facilities and School Structure Study.

"They did indicate that they would be back in touch with us in December of this year to see if we've been accepted into the program," Curtis reported.

"So the senior study was a preliminary visit, if you will, in their decision-making process."

Following a successful SOI, the next step would be a feasibility study to determine the specific needs and parameters of the project, costing about $1.5 million and partially covered by the state. There is a potential for 80 percent reimbursement through the MSBA, who will decide on the project by the end of the year.


Tags: HVAC,   school building committee,   

If you would like to contribute information on this article, contact us at info@iberkshires.com.

Letter: Is the Select Board Listening to Dalton Voters?

Letter to the Editor

To the Editor:

A reasonable expectation by the people of a community is that their Select Board rises above personal preference and represents the collective interests of the community. On Tuesday night [Nov. 12], what occurred is reason for concern that might not be true in Dalton.

This all began when a Select Board member submitted his resignation effective Oct. 1 to the Town Clerk. Wishing to fill the vacated Select Board seat, in good faith I followed the state law, prepared a petition, and collected the required 200-plus signatures of which the Town Clerk certified 223. The Town Manager, who already had a copy of the Select Board member's resignation, was notified of the certified petitions the following day. All required steps had been completed.

Or had they? At the Oct. 9 Select Board meeting when Board members discussed the submitted petition, there was no mention about how they were informed of the petition or that they had not seen the resignation letter. Then a month later at the Nov. 12 Select Board meeting we learn that providing the resignation letter and certified petitions to the Town Manager was insufficient. However, by informing the Town Manager back in October the Select Board had been informed. Thus, the contentions raised at the Nov. 12 meeting by John Boyle seem like a thinly veiled attempt to delay a decision until the end of January deadline to have a special election has passed.

If this is happening with the Special Election, can we realistically hope that the present Board will listen to the call by residents to halt the rapid increases in spending and our taxes that have been occurring the last few years and pass a level-funded budget for next year, or to not harness the taxpayers in town with the majority of the cost for a new police station? I am sure these issues are of concern to many in town. However, to make a change many people need to speak up.

Please reach out to a Select Board member and let them know you are concerned and want the Special Election issue addressed and finalized at their Nov. 25 meeting.

Robert E.W. Collins
Dalton, Mass.

 

 

View Full Story

More Pittsfield Stories