MassDOT: South County Construction Operations
STOCKBRIDGE, Mass. — The Massachusetts Department of Transportation (MassDOT) is announcing various construction operations on I-90 eastbound and westbound for guardrail and bridge repair work, as well as tree trimming.
The work will take place from Monday, Dec.23, through Friday, Dec.27, during the following scheduled hours:
West Stockbridge/Stockbridge
- Guardrail repair work will be conducted on I-90 westbound from mile marker 4.0 to 7.0, utilizing lane closures, during overnight hours on Monday, Dec.23, from 7:00 p.m. to 5:00 a.m. the following morning.
- Guardrail repair work will be conducted on I-90 eastbound from mile marker 0.8 to 7.0, utilizing lane closures, during overnight hours on Monday, Dec.23, from 7:00 p.m. to 5:00 a.m. the following morning.
West Stockbridge
- Bridge repair work will be conducted on I-90 eastbound from mile marker 0.8 to 3.0, utilizing lane closures, during overnight hours on Monday, Dec.23, from 7:00 p.m. to 5:00 a.m. the following morning.
- Guardrail repair work will be conducted on I-90 westbound at mile marker 3.0, utilizing lane closures, during overnight hours on Sunday, Dec.22, and Monday, Dec.23, from 8:00 p.m. to 4:00 a.m., the following morning, with all work concluding by 4:00 a.m. on Tuesday, Dec.24,
- Guardrail repair work will take place on I-90 westbound at mile marker 3.0 at the exit 3 off-ramp, with shoulder closure and narrowed ramp conditions, but the ramp will remain open on Monday, Dec.23, from 7:00 a.m. to 3:30 p.m.
Stockbridge
- Guardrail repair work will be conducted on I-90 westbound at mile marker 4.5, utilizing lane closures, on Sunday, Dec.22, and Monday, Dec.23, from 8:00 p.m. to 4:00 a.m., the following morning, with all work concluding by 4:00 a.m. on Tuesday, Dec.24,
Otis
- Guardrail repair work will be conducted on I-90 westbound at mile marker 19.4, utilizing lane closures, on Sunday, Dec.22, and Monday, Dec.23, from 8:00 p.m. to 4:00 a.m., the following morning, with all work concluding by 4:00 a.m. on Tuesday, Dec.24,
West Stockbridge/Stockbridge/Lee
- Tree trimming will be conducted on I-90 eastbound from mile marker 0.0 to 10.0, utilizing shoulder closures, on Monday, Dec.23, Thursday, Dec.26, and Friday, Dec.27, from 7:00 a.m. to 3:30 p.m. each day.
Tags: MassDOT,