image description
The Board of Selectmen heard an update on the progress being made at the outdoor center in the Greylock Glen on Wednesday.

Greylock Glen Outdoor Center 90% Complete

By Tammy DanielsiBerkshires Staff
Print Story | Email Story
ADAMS, Mass. — The Greylock Glen Outdoor Center is about 90 percent finished with an anticipated completion date in August. 
 
Matthew Sturz of owner's project manager Colliers International updated the Selectmen on the project's progress via Zoom on Wednesday. 
 
"We'll work with the town to determine exactly the logistics of that," he said in response to questions about the opening. "I think that there's certainly interest in getting the facility open as soon as it can open. But we do need to conclude the construction activities ... it's not federally advisable to have construction activity going on with the public."
 
The completion will depend on getting a certificate of occupancy for the 10,000-square foot facility.
 
The  $8.3 million project is running eight months behind the expected schedule, Sturz said, largely because of permitting with the state Department of Environmental Protection that required an extensive environmental review of endangered species, working with National Grid to determine how solar will be integrated into the project, and the need for a water system for both potable water and fire suppression. 
 
"Transformers and all manner of electrical switchgear is being significantly impacted by supply chain issues throughout the construction industry," said Sturz. "So coordinating those items up front took a little bit longer than anticipated."
 
A 350,000-gallon water tank is being constructed on the grounds to provide water with completion expected by July or August. 
 
The outdoor center will consist of retail and education wings, a food service area, space for support services and an outdoor pavilion. Once the construction phase ends, the focus will shift to mechanicals and interior, then final grading and site work. 
 
Selectman Joseph Nowak pressed the Sturz on the decision not to put solar panels on the roof. He had brought up the issue at several meetings, including a budget meeting, after the board voted to expend $25,000 for a geotechnical survey to support solar carports. 
 
"The solar portion of this, I think, was not originally intended to be on the building itself," Sturz said. "We did have a feasibility study that we commissioned with to determine how best to integrate solar into the project, which I think is what you're referring to, and concluded that sort of the among the most cost-effective solar implementations will be to put it on the building.
 
"With the project currently being under construction, trying to integrate multiple design efforts was kind of impractical. And that coupled with the difficulty of coordinating all of that information with the National Grid load letter in order to avoid delays because electrical transformers can literally take years."
 
Sturz said it was determined that because of the large solar farms coming online in Western Massachusetts, the grid didn't have the capacity to absorb the additional power. The town's special projects manager Donna Cesan added that the engineers found the roof was not suitable in size or design to handle the amount of solar panels needed to generate the power.  
 
"It just seemed the smart decision was to have standalone solar carports and those could be done later and not interfere with the progress and the schedule of the building," said Cesan. "If I've failed to inform the board properly, I apologize for that. But I think and I do feel very strongly it was the right decision." 
 
She thought inexpensive electricity could still be achieved for the building even with fewer panels on the carports because the building itself will be so energy efficient.
 
Sturz said the building was well on its way to achieving a net-zero goal even without the solar. A test of the building's envelope found it had "extremely tight tolerance in excess of what's known as the Passive House standard (for energy efficient construction)." .
 
"It gives us a significant part of the way towards achieving net zero," he said.
 
Selectman Richard Blanchard asked if the building is too tight and unable to breathe. Sturz said the shell of the building is very tight but the integrated ventilation system will ensure fresh air into the outdoor center.
 
The quality of workmanship under Souliere & Zepka Construction and its subcontractors has been "exceptional" with great attention to detail, he added. "We are seeing by virtue of the fact that the schedule itself has not slipped despite a couple of challenges that we've encountered.
 
"We're seeing strong teamwork between the general contractor and their subcontractors. So that's encouraging to see."
 
Colliers has a construction representative onsite reviewing the work and Sturz said they could see the quality of the work from the very beginning with the concrete being poured. More recently, the masonry subcontractor has been doing mockups of stone and mortar for the fireplace to ensure it met the aesthetic expectations of the design team. 
 
Town Administrator Jay Green took time to thank Sturz for his work on the outdoor center, noting that it would be his last project for Colliers as he is leaving the firm. Sturz has also been the manager for the Greylock School project in North Adams. 
 
In other business, the board also confirmed the hiring of Robert Wojcik as the new building and grounds superintendent for the glen. Wojcik has 37 years with the town's Department of Public Works, beginning as a seasonal laborer in 1987 and is currently a working foreman. He will start at a salary of $74,000.
 
Green said Wojcik's institutional knowledge and skill will be continue to be of benefit to the town. "The hiring panel had no reservation that Mr. Wojcik is up for the challenge and will make the town of Adams proud," he said.
 
"Thank you for the opportunity," said Wojcik. "I won't let you down."
 
Nowak raised questions about the hiring process, saying he was uncomfortable with Wojcik's bosses doing the interviews. 
 
"But I particularly don't like the process when your immediate boss is across from you, and our town administrator that you work for, and it just seems like some of the jobs are like a coronation, at least in my opinion," said Nowak. "I've known you for a long time but I also have to look out for the town when we give interviews that don't seem appropriate to me to have, you know, your immediate boss, town administrator and, you know, Mike interviewing ... then the salary bothered me a little bit but Jay explained it to us."
 
It was also noted that Wojcik's daughter is the town's finance director. Green said the director had been "isolated" from conversations about the hiring and that the process had complied with the regulations regarding relationships. 
 
Out of 12 applicants, five were interviewed and three were selected as finalists. Glen Executive Director Michael Wynn and DPW Operations Manager Timothy Cota did the initial screening. 
 
The town normally posts jobs internally first but had not in this case. If it had, and Wojcik had applied then, he would have received first consideration, Green said, and that all three finalists for the post were related somehow to someone within town government.
 
"We are a small community and I will also indicate that I've had, under my own volition and decision to do so, I had a conversation with our labor attorney about the process we followed and he had no exception with it."
 
Correction: Selectman Joseph Nowak's concerns were about who did the interviewing for the glen superintendent's position, not his relationships. This has been corrected in the article. iBerkshires regrets the error. 

Tags: Greylock Glen,   

If you would like to contribute information on this article, contact us at info@iberkshires.com.

Special Minerals Agrees to Pay Adams, River Groups Over River Discharge

Staff ReportsiBerkshires

Adams plans to use the $50,000 it will get in the consent decree toward the removal of the Peck's Road Dam. 
BOSTON — Specialty Minerals is expected to pay $299,000 for a discharge of calcium carbonate into the Hoosic River nearly three years ago in a consent decree with the Attorney General's Office. 
 
The river turned visibly white from Adams to the Vermont state line from the mineral that leaked out from the plant's settling ponds on Howland Avenue in November 2021. 
 
Calcium carbonate, also known as chalk or limestone, is not toxic to humans or animals. However, the sudden discoloration of the water alarmed local officials and environmentalists and prompted an emergency session of the Northern Berkshire Regional Emergency Planning Committee. 
 
"We allege that this company violated its permits, disregarded federal and state law, and put the Hoosic River — a resource cherished by the Adams community — at risk," said AG Andrea Campbell in a statement. "I am grateful for this collaboration with our state agency partners and committed to holding polluters accountable and working to bring resources back to communities disproportionately impacted by environmental harms."   
 
If approved by the U.S. District Court of Massachusetts, the consent decree will require Specialty Minerals to pay a total of $299,000, which includes payments to the town of Adams and three community groups in Northern Berkshire County that will be used to benefit water quality and prevent stormwater impacts. 
 
Once approved, most of the settlement would fund multiple projects to benefit water quality, including infrastructure improvements and native plantings to mitigate stormwater impacts in the Hoosic River Watershed. Specifically, the proposed settlement provides for: 
  • $50,000 to the town of Adams for infrastructure improvements in a tributary of the Hoosic River
  • $50,000 to Hoosic River Revival for stormwater mitigation projects  
  • $50,000 to Hoosic River Watershed Association for a native plant garden and other projects to mitigate stormwater impacts and benefit water quality 
  • $50,000 to Sonrisas to fund invasive plant removal and native plant habitat establishment at Finca Luna Búho, a community land project that centers the voices and prioritizes the decision-making of those living in marginalization. 
It will also provide $30,000 in civil assessments to the state's Natural Heritage Endangered Species Fund and $20,000 in civil penalties for violation of state law, as well as $49,000 to offset the costs of the AG's enforcement efforts. 
 
View Full Story

More Adams Stories