Pittsfield Street Improvement Project: Oct. 18-23
- Oct. 18: Lowering structures on Crane Avenue from Oak Hill Road moving west, approximately 2000 feet, towards 553 Crane Avenue.
- Oct. 21: Milling Crane Avenue (same section as above)
- Oct. 22: Paving of Crane Avenue (same section as above)
- Oct. 23: Curb installation on Crane Avenue (same section as above)