Milling and Paving Operations on Merrill Road

Print Story | Email Story
PITTSFIELD, Mass. — The Massachusetts Department of Transportation (MassDOT) is announcing that it will be conducting milling and paving operations on a section of Merrill Road (Route 9) in Pittsfield. 
 
The work will take place from approximately 400 feet west of the East Street and Merrill Road intersection to the intersection of Junction Road. 
 
The work is scheduled to begin on Tuesday, September 3, and is expected to last approximately four weeks. Work will be conducted from 7:00 a.m. to 3:30 p.m. each day. One lane in each direction will be maintained throughout the project.
 
The work will include removing the existing pavement surface, repairing and adjusting drainage structures, installing new pavement, and applying new traffic markings.
 
Drivers traveling through the affected areas should expect delays, reduce speed, and use caution.
 
Appropriate signage, law enforcement details, and messaging will be in place to guide drivers through the work area.
 
All scheduled work is weather dependent and subject to change without notice.

Tags: MassDOT,   

If you would like to contribute information on this article, contact us at info@iberkshires.com.

Dalton Division Road Project in Pre-25 Percent Design Stage

By Sabrina DammsiBerkshires Staff
DALTON, Mass. — The town's engineers say there is still time to work through the Dalton Division Road project’s design and permitting process. 
 
In December, the Select Board voted to advocate for Concept A, which would have sidewalks on both sides, a 5-foot bike lane in the road on both sides with a buffer, and a 2-foot painted buffer between the vehicle lane and in the bike lane. They also recommended the two-way stop control option. 
 
Since that decision, there have been sentiments to revisit this decision to reduce the cost and improve safety at the intersection off Williams Street, Washington Mountain Road, and Mountain Road. 
 
The original vote would have been the most expensive and "certainly not" the engineer or the state's "preferred design," Town Manager Thomas Hutcheson said during a meeting in November. 
 
During last week's Select Board meeting, Fuss & O'Neil project manager and senior traffic engineer Steve Savaria represented the options, explained potential obstacles, and demonstrated the next steps. Present board members have yet to vote on their final choice. 
 
The project is still in the pre-25 percent design stage and is currently on the fiscal year 2029 Transportation Improvement Program list, so there is "plenty of time" to work out the details. 
 
Since the original vote, some board members have shifted their opinion toward advocating for the most feasible and timely option with a "path of least resistance to get this project done." 
 
View Full Story

More Pittsfield Stories