Crosby Elementary has been selected as a the possible site of a combined Crosby and Conte elementary grade-span school.

Pittsfield's Crosby Elementary Eyed For Combined School Site

By Brittany PolitoiBerkshires Staff
Print Story | Email Story

PITTSFIELD, Mass. — Crosby Elementary School is staged for a statement of interest that could open a revamped campus in 2029 as part of larger plans to restructure the district

Superintendent Joseph Curtis on Wednesday presented the details of a potential SOI to the Massachusetts School Building Authority for the elementary school that would combine Conte Community School and Crosby onto one campus with two buildings and shared facilities.

"We are cautious and saying if everything moves along as we would hope that we have the potential opening of a new school facility on the Crosby site in 2029," he said.

Following approvals from the committee and the City Council, a rough timeline shows a feasibility study in 2026 with design and construction ranging from 2027 to 2029. School leaders have mapped out formal opportunities for collaboration with both entities ahead of the SOI due date in April.

"This is exciting. I know you've been working on this a long time," Committee member Sara Hathaway said.

"It's very exciting," Curtis replied. "When we think about our current attendance districts, I really feel it divided our city quite a bit and to be able to widen that net and have our student population certainly be much more diversified in elementary and then completely diversified if we move to a 5,6,7, 8 division of our middle schools, where all of our students will attend one school for Grades 5 and 6 and then 7 and 8. It's really moving forward where we need to be."

The MSBA requires that projects meet one or more of eight outline priorities. The most relevant priority to this effort is "replacement or addition to obsolete buildings in order to provide a full range of programs consistent with state and approved local requirements as determined in the judgments of the authority."

Crosby was identified as having the greatest opportunity for school construction, as it has a large area to build on with little disruption and yields potential for a lower and upper elementary school on the same site.

Curtis explained that school attendance zones are a point of discussion for the entire school district and for this project.

Currently, eight attendance zones designate where a student will go to elementary school. Part of the vision is to collapse those zones into three with hopes of building a plan that incorporates partner schools in each attendance zone.

The West Side zone can potentially have both partner schools, Crosby and Conte, on the same site.  These partner schools could share several common spaces including the gym, cafeteria library, and potential administrative offices which could result in a reduction in costs for maintenance.

This plan has the potential to house Grades pre-K to first grade in one school and Grades 2 to 4 in another with both having their own identities and administrations.

"As it stands currently, the main statement of interest will be related to Crosby Elementary School but a statement of interest would also be submitted on Conte Community School," Curtis said.

"We do have to submit two because our proposal would require we combine both schools onto one site."



The MSBA receives 60 to 70 proposals every year and typically between 15 and 20 are accepted, he said, so just because the district is authorized to submit a statement of interest does not guarantee that the project will be accepted.

If Curtis is authorized by the School Committee to submit an SOI by April 12, the status will be known by December. Following that, a roughly $1 million feasibility study would need to be conducted.

"We are doing a restructuring study, which you'll see that is an important part or would be an important part of our statement of interest," he added, as it shows the MSBA that the entire school district, its structure, attendance zones, and grade spans are being studied.

A joint City Council and School Committee information workshop on the SOI and restructuring project has been proposed for March 6 followed by the committee's vote on the SOI on March 13 and the council's vote on March 36. Curtis emphasized that these dates are approximate.

DRA Architects, which was hired for the restructuring, is drafting a long-term plan for the district that extends to 2050, suggesting possible projects in order or priority. Crosby is at the top of the list.

"The spacing requirements that the MSBA puts forth as as guidelines for a new building project, we have been comparing those guidelines to our existing buildings and even the renovated buildings are all very undersized for today's needs," Curtis said, adding that roughly every renovated school would need to double in size to meet the spacing guidelines.

Chair William Cameron advocated for a walk-through of both buildings with the City Council, which will be held.

Various grade-span models for the district have been presented through community meetings and ultimately, the School Committee will decide on it.

"The reorganization models with the maps and so forth, that's not done by administrative fiat. That has to be voted by the school committee to keep schools open or closed, to change the grade structure in schools, any significant change in the instructional program, all of those things require school committee action in order to be affected," he added.

"So I didn't want people to think that everything you saw was basically a done deal. Virtually nothing is a done deal at this point."

Curtis said it is not necessary to make the grade alignment decisions before the statement of interest, as the district is "demonstrating that we have done a capacity restructuring study and here are the possibilities so that MSBA knows that we have done our work before the actual statement."

The conversation also drifted into the work needed at Pittsfield High School.  Curtis reported that maintenance issues at PHS will be discussed by the School Building Needs Commission and that the school's renovation is currently priced at around $120 million. 


Tags: Crosby School,   Pittsfield Public Schools,   

If you would like to contribute information on this article, contact us at info@iberkshires.com.

Daly Announced as CEO of Pittsfield Co-op

PITTSFIELD, Mass. — Pittsfield Cooperative Bank has named Michael P. Daly its chief executive officer. A friend and customer of the institution since the 1980s, Daly will help develop strategies for ongoing success.
 
"Pittsfield Cooperative Bank appreciates Mike's willingness to step in and assist us," said Board Chair John J. Martin Jr., partner at Martin Hochberg & Cianflone. "We look forward to his help in creating and executing a thoughtful plan for the future and continued profitability." 
 
A Pittsfield native and Berkshire resident, Daly said he is motivated to step out of retirement because of his deep roots and friendships in the community and at the bank.
 
"This arrangement wouldn't be happening if it wasn't in Pittsfield, Mass., and with Pittsfield Cooperative Bank," Daly said. "I have had a long history with the bank, and I am thrilled to return and build on the success of this community bank."
 
It was announced last week that Jay Anderson, CEO for 15 years, was stepping down for health reasons.  
 
Previously, Daly was chairman, president and CEO of Berkshire Bank in Pittsfield. He began his career there in 1986 as a commercial lender. The bank went public in 2000. In 2002 he ascended to president and CEO. During his 16-year tenure, he grew the bank from approximately $1 billion in assets to a company with over $12 billion in assets.
 
"I loved my time at Berkshire," Daly said. "I will always be grateful to my board members and all of the employees for what we shared and accomplished in the community." Now, he said, "The chance to return to my hometown with a community bank is a really compelling opportunity."
 
View Full Story

More Pittsfield Stories