City of Pittsfield Street Improvement Project Schedule for August 1 to 4
PITTSFIELD, Mass. — Please be advised of the following work that will take place August 1-4, as part of the city of Pittsfield’s 2022 Street Improvement Project.
Monday, August 1: milling on East Street on the east side. (from Park Square to the East St./Elm St./Fourth St. intersection)
Tuesday, August 2: milling on East Street on the west side. (from Park Square to the East St./Elm St./Fourth St. intersection)
Wednesday, August 3: first coat of paving on East Street on the east side.
Thursday, August 4: first coat of paving on East Street on the west side.
On-street parking is prohibited during this work between the hours of 12a.m.-Noon. Please note there will be impacts to traffic.
The schedule is subject to change based on weather conditions. The city of Pittsfield thanks you for your patience during this time.