image description
A horizontal geothermal system will cost nearly $3.5 million less than the initial vertical, or well, system. The lines will run underneath the parking area and field.

Geothermal Switch Lowers System Cost for North Adams School Project

By Tammy DanielsiBerkshires Staff
Print Story | Email Story
NORTH ADAMS, Mass. — The cost estimates for the Greylock School project are coming in slightly under budget — including the planned geothermal system. 
 
Initial estimates for the alternative heating system came in at $5 million — $3 million over budget. 
 
"We realized this is never going to work at this cost and we needed to think about the system a little differently," said Jesse Saylor of TSKP Studio, the school's designer, told the School Building Committee on Tuesday. "So we reached out to the well designers and came up with an alternative design, which we feel is much more appropriate for your site."
 
A redesign from using vertical wells to horizontal wells, reduced the costs to $1.5 million.
 
Saylor explained that the drillers had gone down more than 440 feet, through soil and more than 200 feet of bedrock and hit the aquifer, which had to be capped off because of the pressure. 
 
"So our design heading into the cost estimate was to shorten the depth of the wells. Let's not penetrate into that aquifer. Let's just go down 400 feet," he said. "They wanted to carry steel casing all the way down the 400 feet of depth, because the concern is that aquifer depth may vary across across your site, and so that was driving up the initial cost."
 
That vertical system would have required 66 wells and cost about $5 million. Instead, the system will now run horizontally at a depth of about 20 to 30 feet. 
 
"We don't get anywhere near the aquifer, and we don't need the bedrock. In this case, we don't have any casing involved," Saylor said. "So this seems like a better fit for our site."
 
The geothermal system will be out of sight below the parking lot on the south side of the new school.  
 
Mayor Jennifer Macksey, chair of the committee, noted her concerns over using the state-mandated geothermal system from the beginning. She asked why the designers hadn't looked at the less expensive horizontal option in the first place. 
 
"While the technology's not new, it's just having enough vendors in the area," said Saylor. "And we believe we have found three that are interested in the project."
 
The approved changes are part the design package being submitted to the Massachusetts School Building Authority on Wednesday. The MSBA will review the documents over the next few weeks. 
 
Overall, the estimators have come up with a total $52,738,200, about $600,000 under the budgeted amount of $53,405,500. 
 
This involved two independent estimators and a reconciliation with the design team to make sure they're looking at the documents in the same way and seeing the same quantities of material.
 
"We're on budget, we're on target," said Tim Alix of owner's project manager Colliers International. "We had to look at maybe doing some things a little bit differently but in the end the number came in with our budget."
 
The numbers will be reviewed again at the 90 percent design phase.
 
Alix said $1.6 million in invoices have been approved to date and, of those, about $940,000 are eligible for reimbursement. He anticipated about $750,000 coming back to the district. 
 
"A little bit less than half of what's been spent to date," he said. "This is kind of expected. That percentage goes up and down as we move through the project and different phases. More items or less items are deemed eligible or ineligible for reimbursement."
 
The district now has signed a funding agreement with the MSBA and can begin entering invoices electronically as they come in. Alex figured about three weeks from submitting bills to receiving reimbursement. 
 
"It's kind of a revolving process," he said. "You're never really spending all of these funds, because you're getting money back on a consistent basis."
 
The project is now moving into the construction document stage and engineering firm Salas O'Brien, with offices in Albany, N.Y., and Hartford, Conn., has been selected by the MSBA as the commissioning consultant. 

Tags: Greylock School Project,   

If you would like to contribute information on this article, contact us at info@iberkshires.com.

Berkshire County Homes Celebrating Holiday Cheer

By Breanna SteeleiBerkshires Staff

There's holiday cheer throughout the Berkshires this winter.

Many homeowners are showing their holiday spirit by decorating their houses. We asked for submissions so those in the community can check out these fanciful lights and decor when they're out.

We asked the homeowners questions on their decorations and why they like to light up their houses.

In Great Barrington, Matt Pevzner has decorated his house with many lights and even has a Facebook page dedicated to making sure others can see the holiday joy.

Located at 93 Brush Hill Road, there's more than 61,000 lights strewn across the yard decorating trees and reindeer and even a polar bear. 

The Pevzner family started decorating in September by testing their hundreds of boxes of lights. He builds all of his own decorations like the star 10-foot star that shines done from 80-feet up, 10 10-foot trees, nine 5-foot trees, and even the sleigh, and more that he also uses a lift to make sure are perfect each year.

"I always decorated but I went big during COVID. I felt that people needed something positive and to bring joy and happiness to everyone," he wrote. "I strive to bring as much joy and happiness as I can during the holidays. I love it when I get a message about how much people enjoy it. I've received cards thanking me how much they enjoyed it and made them smile. That means a lot."

Pevzner starts thinking about next year's display immediately after they take it down after New Year's. He gets his ideas by asking on his Facebook page for people's favorite decorations. The Pevzner family encourages you to take a drive and see their decorations, which are lighted every night from 5 to 10.

In North Adams, the Wilson family decorates their house with fun inflatables and even a big Santa waving to those who pass by.

The Wilsons start decorating before Thanksgiving and started decorating once their daughter was born and have grown their decorations each year as she has grown. They love to decorate as they used to drive around to look at decorations when they were younger and hope to spread the same joy.

"I have always loved driving around looking at Christmas lights and decorations. It's incredible what people can achieve these days with their displays," they wrote.

They are hoping their display carries on the tradition of the Arnold Family Christmas Lights Display that retired in 2022.

The Wilsons' invite you to come and look at their display at 432 Church St. that's lit from 4:30 to 10:30 every night, though if it's really windy, the inflatables might not be up as the weather will be too harsh.

In Pittsfield, Travis and Shannon Dozier decorated their house for the first time this Christmas as they recently purchased their home on Faucett Lane. The two started decorating in November, and hope to bring joy to the community.

"If we put a smile on one child's face driving by, then our mission was accomplished," they said. 

View Full Story

More North Adams Stories