MassDOT: South County Road Construction
- Paving operations will be conducted on I-90 westbound from mile marker 21.0 to 24.0 on Monday night, Aug. 5, from 6:00 p.m. to 6:00 a.m. the next morning. The work is expected to conclude by 6:00 a.m. on Tuesday, Aug. 6.
- Paving operations will be conducted on I-90 eastbound from mile marker 21.0 to 23.0 from Tuesday night, Aug. 6, through Thursday night, Aug. 8, from 6:00 p.m. to 6:00 a.m. the next morning. The work is expected to conclude by 6:00 a.m. on Friday, Aug. 9.
- Bridge work will be conducted on I-90 eastbound and westbound at mile marker 22.5 from Monday night, Aug. 5, through Thursday night, Aug. 8, from 7:00 p.m. to 5:00 a.m. the next morning. The work is expected to conclude by 5:00 a.m. on Friday, Aug. 9.
- Guardrail work will be conducted on I-90 westbound from mile marker 1.0 to 6.5 from Monday night, Aug. 5, through Thursday night, Aug. 8, from 7:00 p.m. to 5:00 a.m. the next morning. The work is expected to conclude by 5:00 a.m. on Friday, Aug. 9.
- Erosion control work will be conducted on I-90 eastbound from mile marker 5.5 to 6.5 from Monday night, Aug. 5, through Thursday night, Aug. 8, from 7:00 p.m. to 5:00 a.m. the next morning. The work is expected to conclude by 5:00 a.m. on Friday, Aug. 9.
- Bridge repair work will be conducted on I-90 westbound from mile marker 2.0 to 3.0 from Monday night, Aug. 5, through Thursday night, Aug. 8, from 7:00 p.m. to 5:00 a.m. the next morning. The work is expected to conclude by 5:00 a.m. on Friday, Aug. 9.
Tags: MassDOT,