Large Solar PV Arrays Likely Not Feasible in Dalton

By Sabrina DammsiBerkshires Staff
Print Story | Email Story
DALTON, Mass. — Large multi-megawatt solar panel photovoltaic array projects are likely not feasible in the near future. 
 
Green Committee member Todd Logan updated the committee last week on his efforts to obtain data to inform the possibility of developing large PV arrays on town properties.
 
The town's Climate Action Plan consultant, Blue Strike Environmental, requested information on what it should focus on when developing the Climate Action Plan. 
 
The company needed data on the town's energy generation capacity to determine the type of feasible projects for the town. 
 
Eversource provided the Green Committee with a distributed generation hosting pre-application report, which it will provide to Blue Strike.
 
The latest information provided granular data, including the substation transformer rating, the substation's circuit voltage and name, the phase available near the site, and the distance from the phase service if it's a single phase. 
 
It also includes standards for the interconnection of distributed generation, including information on aggregate connected facilities that have not yet been interconnected, the interconnecting customer's network types and nearby feeders, and potential system constraints that may impact the proposed facility, among other things. 
 
The Eversource data informs which more tangible and feasible projects Blue Strike Environmental should focus on. 
 
The Eversource representative also informed Logan that due to a group of very large grid-connected energy generation projects already in the queue, a study has to be conducted to see the impact on the Eversouce circuit that serves Dalton. 
 
The Eversource representative indicated that the grid infrastructure would likely need to be upgraded to accommodate these projects. 
 
Until the study is complete, circuit 18C BERKSHIRE's hosting capacity will be unclear. This will make it unclear what type of projects the town is able to do in the future, Logan said. 
 
If the upgrades are needed, each energy project will have to contribute to the cost of the upgrades, he said. 
 
The Eversource representative could not give Logan many details about the project, such as the timeframe and scope. 
 
In other news: 
 
The installation of electric vehicle (EV) charging stations at the Community Recreation Association has been delayed, committee member Antonio Pagliarulo said. 
 
Dave Callahan of Universal EV Charging Station, who is overseeing the project, is ready to install the stations, but Eversource is delayed, Pagliarulo said. 
 
It is unclear when the project will be completed but they hope to have it done in August.
 
Committee members suggested that the town decide which composting station model to use for its transfer station, either the Egremont Transfer Station's model or Williamstown compost's model.
 
They also would like a Green Committee representative to be part of the transfer station study. 

Tags: green committee,   solar array,   

If you would like to contribute information on this article, contact us at info@iberkshires.com.

Habitat For Humanity Modular Homes Coming to Robbins Ave.

By Brittany PolitoiBerkshires Staff

The homes will be available for residents earning between 55 and 65 percent of the area median income. 

PITTSFIELD, Mass. — The first of two below-market modular homes arrived on the West Side on Thursday, and both are expected to be move-in ready this summer.

The other is expected next week.

Central Berkshire Habitat for Humanity is building two below-market condominiums at 112 Robbins Ave. for families earning between 55 percent and 65 percent of the area median income. Monthly costs for the three- and four-bedroom units are expected to be less than $1,500 with Habitat's subsidies.

Modulars allow for quicker construction to get more families into quality, affordable housing.

"Just because we have such an aggressive schedule this year, we are doing many modulars in addition to the stick-built that we usually do," communications manager Erin O'Brien explained.

Just this year, the nonprofit is constructing five homes in Pittsfield and 10 in Housatonic.

The two homes at 112 Robbins Ave. will come to $148,000 for a three-bedroom with the 20 percent subsidy and $156,000 for a four-bedroom. Similar homes in the Pittsfield area are valued between $225,000 and $250,000.

While prices are subject to change, the three-bedroom condo will cost owners about $1,430 per month and the four bedroom $1,495 per month, compared to renting in the city for more than $1,800 per month. Habitat noted that this provides a potential annual savings of $4,500 to $6,000, while building equity and long-term financial security.

The eligibility range between 55 percent and 65 percent AMI is said to support families who earn too much for most housing subsidies but still struggle to afford market-rate homes.

View Full Story

More Pittsfield Stories