Large Solar PV Arrays Likely Not Feasible in Dalton

By Sabrina DammsiBerkshires Staff
Print Story | Email Story
DALTON, Mass. — Large multi-megawatt solar panel photovoltaic array projects are likely not feasible in the near future. 
 
Green Committee member Todd Logan updated the committee last week on his efforts to obtain data to inform the possibility of developing large PV arrays on town properties.
 
The town's Climate Action Plan consultant, Blue Strike Environmental, requested information on what it should focus on when developing the Climate Action Plan. 
 
The company needed data on the town's energy generation capacity to determine the type of feasible projects for the town. 
 
Eversource provided the Green Committee with a distributed generation hosting pre-application report, which it will provide to Blue Strike.
 
The latest information provided granular data, including the substation transformer rating, the substation's circuit voltage and name, the phase available near the site, and the distance from the phase service if it's a single phase. 
 
It also includes standards for the interconnection of distributed generation, including information on aggregate connected facilities that have not yet been interconnected, the interconnecting customer's network types and nearby feeders, and potential system constraints that may impact the proposed facility, among other things. 
 
The Eversource data informs which more tangible and feasible projects Blue Strike Environmental should focus on. 
 
The Eversource representative also informed Logan that due to a group of very large grid-connected energy generation projects already in the queue, a study has to be conducted to see the impact on the Eversouce circuit that serves Dalton. 
 
The Eversource representative indicated that the grid infrastructure would likely need to be upgraded to accommodate these projects. 
 
Until the study is complete, circuit 18C BERKSHIRE's hosting capacity will be unclear. This will make it unclear what type of projects the town is able to do in the future, Logan said. 
 
If the upgrades are needed, each energy project will have to contribute to the cost of the upgrades, he said. 
 
The Eversource representative could not give Logan many details about the project, such as the timeframe and scope. 
 
In other news: 
 
The installation of electric vehicle (EV) charging stations at the Community Recreation Association has been delayed, committee member Antonio Pagliarulo said. 
 
Dave Callahan of Universal EV Charging Station, who is overseeing the project, is ready to install the stations, but Eversource is delayed, Pagliarulo said. 
 
It is unclear when the project will be completed but they hope to have it done in August.
 
Committee members suggested that the town decide which composting station model to use for its transfer station, either the Egremont Transfer Station's model or Williamstown compost's model.
 
They also would like a Green Committee representative to be part of the transfer station study. 

Tags: green committee,   solar array,   

If you would like to contribute information on this article, contact us at info@iberkshires.com.

Pittsfield Panel Supports $280K Winter Maintenance Deficit

By Brittany PolitoiBerkshires Staff

PITTSFIELD, Mass. — The finance subcommittee recently OK'd a $280,000 transfer to the Department of Public Services for winter maintenance overages with the understanding that the ask may be higher when it goes to the full City Council.

The account is permitted to operate a deficit and has overspent $781,220.  At the time of the request, $501,220 was recovered and the $280,000 will address the rest, with $200,000 coming from the Fire Department and $80,000 from the building maintenance department.

It was explained that the order was about two weeks old and some of the recovered funds had to be diverted to get to the close of the fiscal year on June 30. Commissioner of Public Services and Utilities Ricardo Morales explained that it is "very, very tight."

"What we would like to do is reserve the right to come back with a new order at the next meeting, having approved this with an understanding or a comment from the committee that there is an understanding that it may come back to the full council with a different figure than the $280,000," Finance Director Matthew Kerwood said..

"It won't be dramatic but it gives us a decent enough breathing room to be able to come back with a solid number so that we're not having to then raise whatever the deficit is, if there is a deficit, on the next year's recap and add it to the next year’s tax rate."

The city has until July 15 to "clean up the books."

He explained that in looking at other departments for turnbacks in fiscal year 2024, there would be sufficient funds from other areas to fill the gap. No more than $100,000 in additional transfers is expected.

"To be clear, at home, there was also an excess deficit of about $800,000, you thought you could cover it from other accounts and you took it out and covered that, then other things came up this spring and summer so you needed that money back," Chair Earl Persip III confirmed so that the audience watching Pittsfield Community Television at home don't think the city is "robbing Peter to pay Paul."

Kerwood confirmed, adding, "Whatever came back, we would still be addressing a deficit in winter operations."

View Full Story

More Pittsfield Stories