image description
Williamstown Fire District Building Committee members, from left, Bob Menicocci, Don Dubendorf, Ryan Housman and Jim Kolesar, participate in the panel's Dec. 20 meeting.
Updated July 27, 2023 05:18PM

Williamstown Fire District's Building Committee Discusses Site Work, Sees Cost Estimate

By Stephen DravisiBerkshires Staff
Print Story | Email Story
WILLIAMSTOWN, Mass. — The Fire District's Building Committee recently saw revised cost estimates for a new station on Main Street and discussed whether the district's site needs to be preloaded to address soil compaction before construction gets underway.
 
The latest estimated bottom line for the project, including so-called "soft costs," is just less than $25 million, according to the district's owners project manager, Colliers International.
 
The latest estimate, dated Dec. 13, of $24.9 million fell in the middle of a range of mid-November numbers from Colliers, which at the time said the project could cost between $21.8 and $28.5 million.
 
Williamstown Fire District officials hope to have the most precise estimate available before they go to voters to ask for bonding authority at a planned Feb. 28 special district meeting.
 
The latest round of projections includes roughly $100,000 for an "early site package" at 562 Main St., the property the district purchased in 2017. That $100,000 ballpark projection referred to the design-cost, on-site monitoring and other expenses beyond typical fill and removal of unusable soils.
 
The expense is not a big surprise. It results from a recent geotechnical study done on the site, and previous estimates have included a contingency to account for work that the geotech findings would require.
 
As it happens, the recent study discovered more potential for compaction than previously known.
 
"The second piece of information, which was surprising to me at least, was the original borings didn't go down as far as we would have liked from an engineering/design standpoint," architect Chris Wante of Pittsfield's EDM told the Building Committee at its Tuesday afternoon meeting. "What [the new borings] found was soils well below the grade are clay material with a high probability for significant settlement.
 
"So when we load with additional fill to bring it up above flood plain and then put a building on top, the geotech analysis showed there could be potential settlement of 6 inches, so the building would sink. Obviously, it's something we needed to address."
 
Wante said the geotechnical engineer hired by the district is advising that the building footprint be preloaded or "surcharged" with 3 feet of soil and then allowed to sit before construction work begins. For three to four months, engineers would then monitor the site to see what compaction occurs before proceeding with construction.
 
He said the surcharge work could fit into the current project timeline as an "early bid" for work that could be done in the spring and summer of next year (assuming voter approval on Feb. 28), while design documents are being finalized. The current timeline does not have construction documents finalized and the project going to bid until October 2023 with the selection of a general contractor next November.
 
"The thought was we'd do an early design package for the site separate from the general contractor scope," Wante said. "So the contractor for the building can hit the ground running Day One."
 
Building Committee member Ryan Housman asked Wante how much difference 3 feet of surcharge could make when the design already calls for between 12 and 15 inches of structural fill.
 
"It's a small percentage of the overall fill," Housman said. "I'm not an expert in geotech. My question is, what would it cost? Can we get a second opinion? Can someone else look at the borings?"
 
Wante said he could pass along the first question to the geotechnical firm and get back to the committee. The latter question prompted a conversation among the committee members about the advantages of a fresh set of eyes.
 
Housman pointed out that the second opinion could suggest a path that either lowers or raises the cost of the preloading work.
 
"If we go to someone else, they might say, 'You need 10 feet of surcharge' instead of 3 feet," he said. "Maybe we have the cheaper option already. We just don't know."
 
His colleagues on the committee and Bruce Decoteau, who the Prudential Committee hired as a local project coordinator to advise the district, agreed that it was worthwhile to pursue the second opinion. And the Building Committee voted unanimously to make that recommendation to the Prudential Committee, which meets on Dec. 28.
 
The Building Committee also recommended that the Prudential Committee authorize the architect to put together an early site package so it is ready to release for bids, if needed, right after the Feb. 28 district meeting.
 
The Building Committee did get some good news on the financial front on Tuesday.
 
District officials had been concerned that the new station's participation in the Solar Massachusetts Renewable Target [SMART] renewable energy credits program might be incompatible with the WFD's stated goal of seeking certification from the International Living Future Institute.
 
But committee member Jim Kolesar reported that the ILFI had told the district it could do both, keeping the district eligible for $372,000 in renewable energy credits over 20 years ($18,600 per year) as a reward for installing solar photovoltaics at the new station.
 
Editor's note: This story updated on July 27, 2023, to provide clarification of a cost estimate cited at the meeting.

Tags: building committee,   fire district,   fire station,   

If you would like to contribute information on this article, contact us at info@iberkshires.com.

Guest Column: Full Steam Ahead: Bringing Back the Northern Tier Passenger Railroad

by Thomas HuckansGuest Column

You only need a glance outside to see a problem all too familiar to Berkshire county: closing businesses, a shrinking population, and a stunning lack of regional investment.

But 70 years ago, this wasn't an issue. On the North Adams-Boston passenger rail line before the '60s, Berkshires residents could easily go to Boston and back in a day, and the region benefited from economic influx. But as cars supplanted trains, the Northern Tier was terminated, and now only freight trains regularly use the line.

We now have a wonderful opportunity to bring back passenger rail: Bill S.2054, sponsored by state Sen. Jo Comerford (D-Hampshire, Franklin, and Worcester), was passed to study the potential for restoring rail from Boston to North Adams. In the final phase of MassDOT's study, the project is acquiring increased support and momentum. The rail's value cannot be understated: it would serve the Berkshire region, the state, and the environment by reducing traffic congestion, fostering economic growth, and cutting carbon emissions. The best part? All of us can take action to push the project forward.

Importantly, the Northern Tier would combat the inequity in infrastructure investment between eastern and western Massachusetts. For decades, the state has poured money into Boston-area projects. Perhaps the most infamous example is the Big Dig, a car infrastructure investment subject to endless delays, problems, and scandals, sucking up $24.3 billion. Considering the economic stagnation in Western Massachusetts, the disparity couldn't come at a worse time: Berkshire County was the only county in Massachusetts to report an overall population loss in the latest census.

The Northern Tier could rectify that imbalance. During the construction phase alone, 4,000 jobs and $2.3 billion of economic output would be created. After that, the existence of passenger rail would encourage Bostonians to live farther outside the city. Overall, this could lead to a population increase and greater investment in communities nearby stops. In addition to reducing carbon emissions, adding rail travel options could help reduce traffic congestion and noise pollution along Route 2 and the MassPike.

The most viable plan would take under three hours from North Adams to Shelburne Falls, Greenfield, Athol, Gardner, Fitchburg, Porter, and North Station, and would cost just under $1.6 billion.

A common critique of the Northern Tier Rail Restoration is its price tag. However, the project would take advantage of the expansion of federal and state funds, namely through $80 billion the Department of Transportation has to allocate to transportation projects. Moreover, compared to similar rail projects (like the $4 billion planned southern Massachusetts East-West line), the Northern Tier would be remarkably cheap.

One advantage? There's no need to lay new tracks. Aside from certain track upgrades, the major construction for the Northern Tier would be stations and crossings, thus its remarkably short construction phase of two to four years. In comparison, the Hartford line, running from Hartford, Conn., to Springfield spans barely 30 miles, yet cost $750 million.

In contrast, the Northern Tier would stretch over 140 miles for just over double the price.

So what can we do? A key obstacle to the Northern Tier passing through MassDOT is its estimated ridership and projected economic and environmental benefits. All of these metrics are undercounted in the most recent study.

Crucially, many drivers don't use the route that MassDOT assumes in its models as the alternative to the rail line, Route 2. due to its congestion and windy roads. In fact, even as far west as Greenfield, navigation services will recommend drivers take I-90, increasing the vehicle miles traveled and the ensuing carbon footprint.

Seeking to capture the discrepancy, a student-led Northern Tier research team from Williams College has developed and distributed a driving survey, which has already shown more than half of Williams students take the interstate to Boston. Taking the survey is an excellent way to contribute, as all data (which is anonymous) will be sent to MassDOT to factor into their benefit-cost analysis. This link takes you to the 60-second survey.

Another way to help is to spread the word. Talk to local family, friends, and community members, raising awareness of the project's benefits for our region. Attend MassDOT online meetings, and send state legislators and local officials a short letter or email letting them know you support the Northern Tier Passenger Rail Project. If you feel especially motivated, the Williams Northern Tier Research team, in collaboration with the Center for Learning in Action (CLiA), would welcome support.

Living far from the powerbrokers in Boston, it's easy to feel powerless to make positive change for our greater community. But with your support, the Northern Tier Rail can become reality, bringing investment back to Berkshire County, making the world greener, and improving the lives of generations of western Massachusetts residents to come.

Thomas Huckans, class of 2026, is a political science and astronomy major at Williams College, originally from Bloomsburg, Pa.

Survey: This survey records driving patterns from Berkshire county to Boston, specifically route and time. It also captures interest in the restoration of the Northern Tier Passenger Rail. Filling out this survey is a massive help for the cause, and all responses are greatly appreciated. Use this link.

View Full Story

More Williamstown Stories