WILLIAMSTOWN, Mass. — The initial estimate for a new fire station came in at just below $18 million, the fire district's Building Committee learned on Wednesday.
But there are a number of unknowns at this stage of the design process, and the committee noted at least one opportunity Wednesday to trim the budget by choosing a gas-fired HVAC system over an electric-powered variable refrigerant flow system.
With the more energy-efficient electric VRF system included, estimator Miyakoda Consulting of Raynham pegged the building cost at $17,909,261 for a cost of $658.07 per square foot, assuming a summer 2023 construction start.
If the district ultimately goes with a gas-fired HVAC unit, the upfront cost of construction could come down by about $500,000, according to Miyakoda's estimate. But, Building Committee member Don Dubendorf noted, the life-cycle costs of operating the station would change depending on the mechanical system.
Ken Romeo of Colliers Engineering and Design, the district's owner's project manager, said he could come up with a life-cycle cost comparison in two or three weeks for the Building Committee to consider.
It will be at least six weeks before the committee has more info on one of the biggest unknowns embedded in that $18 million estimate.
EDM's Tim Eagles and Chris Wante, who briefed the Building Committee on Wednesday, said much of a 13 percent "design contingency" in the initial estimate was due to the lack of complete geotechnical studies for the Main Street (Route 2) property where the district hopes to build a new station.
"The biggest uncertainty is the site and soil conditions," Wante said. "Once we get the final geotech report, it will help us know what kind of site prep we need. Are there materials out there that are unknown in terms of unsuitability?"
In part due to the unknown cost of site work, Miyakoda built in a $1.7 million design contingency.
"A design contingency is the estimator's way of saying, 'We don't have all the design information yet,'" Eagles said. "Thirteen percent is a pretty healthy number."
Miyakoda was hired by EDM to estimate the cost of the project. The Prudential Committee, which governs the fire district and appointed the Building Committee, is considering, on Romeo's advice, hiring a second estimator to provide another opinion on projected costs at future stages of the design process.
The current design of the building calls for about 27,215 square feet in two stories with an elevator and six bays for fire trucks with four "drive through" bays with access in the front and rear so trucks don't need to back into the station as they do at the district's current cramped and out-of-date facility on Water Street.
Romeo pointed out to the committee that the estimate it saw on Wednesday referred only to the building itself and the pavement around the structure. It did not include elements like a new radio tower and solar panels, which the district is planning in an effort to make the new station a net-zero building and eligible for green building certification through one of the industry's certifying agencies.
Wednesday's meeting at the Water Street station was the first time any of the Building Committee members saw the numbers, but members did query the architects on some of the assumptions behind them as well as what other costs might fall outside the building estimate.
One so-called "soft cost" that was not factored into Miyakoda's estimate was building permitting.
Dubendorf asked whether the fire district had a commitment from the town about its intention on the permitting question. He recalled that the issue was a point of contention the last time a municipal entity apart from town government did a building project in town.
"I don't want to let that slip," Dubendorf said. "We should have a conversation with [Town Manager Robert Menicocci]. It became a public controversy with the school, and we don't want to let that happen again."
In addition to all the detail questions, Dubendorf also asked Romeo and the project's three architects – Wante, Eagles and Bob Mitchell of Voorheesville, N.Y.,'s Mitchell Associates – for their impression of the bottom line in the estimate.
"This does not surprise us," Eagles said.
"I don't think it's going to get better," Mitchell said. "This is the new reality of building."
If you would like to contribute information on this article, contact us at info@iberkshires.com.
Your Comments
iBerkshires.com welcomes critical, respectful dialogue. Name-calling, personal attacks, libel, slander or foul language is not allowed. All comments are reviewed before posting and will be deleted or edited as necessary.
No Comments
Williamstown CPA Requests Come in Well Above Available Funds
By Stephen DravisiBerkshires Staff
WILLIAMSTOWN, Mass. — The Community Preservation Committee faces nearly $300,000 in funding requests for fiscal year 2026.
Problem is, the town only anticipates having about $200,000 worth of funds available.
Seven non-profits have submitted eight applications totaling $293,797 for FY26. A spreadsheet detailing both FY26 revenue and known expenses already earmarked from Community Preservation Act revenues shows the town will have $202,535 in "unrestricted balance available" for the year that begins on July 1.
Ultimately, the annual town meeting in May will decide whether to allocate any of that $202,535.
Starting on Wednesday, the CPC will begin hearing from applicants to begin a process by which the committee drafts warrant articles recommending the May meeting approve any of the funding requests.
Part of that process will include how to address the $91,262 gap between funds available and funds requested. In the past, the committee has worked with applicants to either scale back or delay requests to another year. Ultimately, it will be the panel's job to send the meeting articles that reflect the fiscal reality.
The individual requests range from a high of $100,000 from the trustees of the town's Affordable Housing Trust to a low of $8,000 from the Williamstown Historical Museum.
Bryant co-founded Remedy Hall in 2023 to lessen the financial burden of community members in need by providing essential items that people may be lacking, including hygiene items, cleaning supplies, clothing, bedding, furniture, and other necessities. click for more
Around 40 people attended the community lighting for the first night of Hanukkah, which fell this year on the same day as Christmas. They gathered in the snow around the glowing blue electric menorah even as the temperature hovered around 12 degrees. click for more
Perhaps no public project has generated as much discussion over the last decade as the proposed new fire station. In September, the long-planned project finally began to come to fruition.
click for more