NORTH ADAMS, Mass. — School officials began their campaign on Wednesday to drum up support for a $10 million school project that could include the renovation of the closed Conte Middle School.

Mayor Richard Alcombright had hoped to present a single option to voters but the Massachusetts School Building Authority had bumped the project from its agenda on Wednesday, delaying a decision until its April meeting. So the five options are being presented over the next month.

There were few in attendance for the presentation. Was it indifference, or has everyone already made up their minds?

The MSBA had charged the city to find a solution for 620 pupils after the middle school was closed in 2009 over budgetary and building issues. Alcombright said the city had serious capital needs, including a new public safety building that could cost $25 million.

"We have so many high-ticket items, we have to start somewhere and this is the one that's in front of us and the only one that's going to give us 80 percent back," said the mayor of the state's reimbursement rate.

The two dozen citizens and officials at Drury High School for a presentation on the project raised questions about costs and safety related to revamping Conte School.

Returning pupils, especially younger ones, to the downtown facility raised concerns over traffic, walking and the loitering of "undesireables" around the school area. The 1916 building had housed high school students and middle school students after the new Drury High was built in 1974.

Councilor Lisa Blackmer said the children walking down steep East Main Street would have to deal with snow-covered sidewalks, cars parked blocking the way and heavy traffic. "These are not middle school students, they're third- and fourth-graders, it's a different mentality," she said. "But considerning the obesity problem in this country, I would like to see kids walking."

 Upcoming Public Meetings

April 5 - 6 p.m., Conte School, agenda item for School Committee meeting
April 7 - 6 p.m., Conte School, lower level, School Building Committee meeting
April 12 - 7:30 p.m., City Hall, agenda on City Council meeting


The mayor and Superintendent of Schools James Montepare said those issues would have to be addressed, but Montepare added most of the children walking would likely be coming east of the school, from a largely residential area.

"Your assuming it's going to be a problem; we don't know if it's going to be a problem," said Montepare. "We haven't got to that point yet. ... We can find solutions."

One man took issue with the preference for renovating Conte despite it being "least desirable" for reconfiguring into teaching clusters, describing it as short-term benefits being placed above long-term educational gains. "It's not good for the kids."

Margo Jones, architect for the project, said the words could have been better chosen and that the other option, to renovate Sullivan School, would be problematic - it would better provide for clustering but would be spread over five floors on a steep hillside. Conte was not ideal but clustering by grades on each floor provided the appropriate space.

The team of Margo Jones Architects ran through a similar presentation to what they offered to the School Building Committee last month, with the addition of a more extensive renovation of Greylock School based on their meeting with the School Building Authority on Feb. 25.

The preferred option of the School Building Committee is the renovation of Conte Middle School into the new kindergarten through Grade 7 format and building a new Greylock School, each to accommodate 310 pupils.

"Since the MSBA meeting, they've expresed some interest in the Greylock site; we've added a 1B, a major renovation," said Kristian Whitsett. The new plan would tear down one section of the aging elementary school, creating more of an L-shaped configuration, and renovate and add on to the building.

Costs for each of the five options includes nonreimbursables (furniture, fees, designs, and any costs related to relocating students) plus an expected overrun. Carl Weber said current MSBA projects have been running under cost by as much as 20 percent because of competitive bidding.

The lowest cost option is the minor renovation of Greylock School and a major renovation of Conte, which comes in at about $44 million and would cost the city  $9.2 million.

The most expensive is the renovation of Conte and construction of a new Greylock School (while children continue to attend the old one). The cost would be $48 million total, $9.8 million to be paid by the city.

The city would have 120 days to confirm support for the project once the MSBA makes a decision on the option it prefers. Carl Weber of Strategic Building, the city's liaison to the MSBA, said the funds, secured from 1 percent of the sales tax, are in place. He couldn't answer to what exactly would happen should the city reject the project but it would probably drop in priority.

"You're still going to have a need but they're looking for communities that want a school, that are going to support a school," he said. "They'd probably go to other districts that had the same needs you do but who support it."

Alcombright said a big concern was that the 80 percent reimbursement would no longer be available if the project is delayed for more years. Montepare added that the elementary schools are "jam-packed."

"Even if you put 350 kids in one new school it wouldn't solve the problem," said Montepare. "It took us three years to get where we are today and we're another three years out ... it's taken three years of constant filing of studies, discussions and trips to Boston to get where we are today." 

     

Support Local News

We show up at hurricanes, budget meetings, high school games, accidents, fires and community events. We show up at celebrations and tragedies and everything in between. We show up so our readers can learn about pivotal events that affect their communities and their lives.

How important is local news to you? You can support independent, unbiased journalism and help iBerkshires grow for as a little as the cost of a cup of coffee a week.

News Headlines
Clarksburg Joining Drug Prevention Coalition
Pittsfield Road Cut Moratorium
Adams Lions Club Makes Anniversary Donations
2nd Street Second Chances Receives Mass Sheriffs Association Award
Swann, Williams College Harriers Compete at NCAA Championships
MassDOT Advisory: South County Road Work
ACB College Financial Aid Event
The Nutcracker At The Colonial Theater
McCann First Quarter Honor Roll
Pittsfield Looks to Update Zoning for ADUs

Voting Registration Deadlines

:: Preliminary Election: Deadline to register is Wednesday, Sept. 7. (Office open from 8 to 8.)
:: General Election: Deadline to register is Tuesday, Oct. 18

Registration can be completed at the city clerk's office at City Hall.

Absentee ballots are now available at the city clerk's office for the Sept. 27 preliminary city election. Voters may come in between the hours of 8 and 4:30 weekdays. Written reguests for mailed ballots can be sent to City Clerk's Office, 10 Main St., North Adams, MA 01247. Deadline for absentee ballots is Monday, Sept. 26, at noon.

The preliminary election will be held Tuesday, Sept. 27, to narrow the field of three mayoral candidates to two. The general election to select nine city councilors and a mayor will be held Tuesday, Nov. 8.


 

City Council

Returned Papers
As of 8/9 at 5 p.m.
 Lisa M. Blackmer* Yes
 Michael Bloom Yes
 Keith Bona* Yes
 David Bond* Yes
 Marie Harpin* Yes
 Alan Marden* Yes
 John Barrett Yes
 Eric R. Buddington Yes
 Nancy P. Bullett Yes
 Robert Cardimino Yes
 Catherine Chaput Yes
 Roland G. Gardner  
 Diane M. Gallese-Parsons  Yes
Shane Gaudreau  
 James B. Gyurasz  Yes
 Michael Hernandez  Yes
 Jennifer Breen Kirsch  Yes
Brian L. Flagg  
 Kellie A. Morrison  Yes
 Greg Roach  Yes
 Gail Kolis Sellers  Yes
18 candidates returned papers
 
 Mayor  
 Richard J. Alcombright*  Yes
 Ronald A. Boucher  Yes
 Robert Martelle  Yes
 Preliminary election will eliminate one
 
 School Committee  
 Mary Lou Accetta* Yes
 Lawrence K. Taft* Yes
 Leonard Giroux Jr.  Yes
 Tara J. Jacobs  Yes
 David Lamarre Yes
   
McCann School Committee  
 George M. Canales Yes

Polling stations

St. Elizabeth's Parish Center

Ward 1
Ward 2
Ward 3
Ward 5

Greylock Elementary School

Ward 4


Draft Budget FY2012

School Budget FY2012

Compensation Plan

Classification Schedule 

Fiscal 2011 Budget

Fiscal 2011 Tax Classification

North Adams Audit 2010

North Adams Single Audit 2010

North Adams Management Letters 2010

North Adams School Building Options



Categories:
Boards & Committees (58)
budget (17)
buildings (12)
City Council (47)
City Hall (8)
Courts (1)
Development (19)
DNA (4)
Downtown (48)
Events (29)
Fun Stuff (32)
Hadley Overpass (2)
Heritage State Park (5)
Housing (2)
Inspections (3)
Library (1)
Mayor (49)
MCLA (8)
MoCA (10)
People (30)
Planning Board (9)
projects (31)
Relations (2)
Schools (24)
Services (14)
stores (19)
Streets (21)
Archives:
Tags:
Election Planning Board Tourism Ordinance Wilco Override Trees Restaurants Jobs Ordinances Armory Conte Airport Sullivan Shopping Transcript Holiday North Adams Main Street Insurance Windsor Lake Hometown Holidays Finance Committee Parking Agenda Campground Contest Fall Foliage Lue Gim Gong Hardman Industrial Park Scarafoni Water Budget School Project Vendors
Popular Entries:
Mattress Maker Facing Foreclosure in N.Y.
Mattress Maker Picks Green Mountain Site
Mattress Company Could Bring 100 Jobs to City
Council OKs Land Buy; Handicapped Signs Coming
City Council Agenda for Aug. 23, 2011
Planning Board to Look at Ordinance Change
City Still Pursuing Bedmaker
Two Challenge Alcombright; Barrett Tries For Council
Transcript Building Sale Gets Final OK
Conte School Option Prompts Protest
Recent Entries:
Public Safety Committee OKs Montana Parking Ban
Eclipse Residents Query Mayor on Collapsing Neighbor
Walmart Expected to Submit Plans for New Store
School Committee Endorses 2-School Plan
North Adams Water Safe to Drink
City Questions Parking Ticket Revenue
City Council Agenda for Aug. 23, 2011
Planning Board to Look at Ordinance Change
Mattress Maker Picks Green Mountain Site
City Still Pursuing Bedmaker