NORTH ADAMS, Mass. — The Shamrock Hangar renovation project, although moving along, will be completed later than expected.
Peter Enzien of Stantec, the engineering firm overseeing the airport improvement projects, told the Airport Commission Tuesday that instead of completing the Shamrock Hangar by December 4, as agreed upon, the project will be pushed out towards the end of the month.
"They are hoping by the end of this week to have the windows in and do some of the electrical work," Enzien said.
"The ultimate goal here is to get the space wrapped up by Christmas to a point where there may be a few miscellaneous things that need to be addressed but the space is mostly complete."
The city purchased the hangar this summer and through Non-Primary Entitlement Funds from the Federal Aviation Authority, the city is renovating the space.
Enzien said the project is being held up by materials that have not yet arrived such as the windows. He said much of the plumbing is complete and the interior walls have been framed.
Enzien said while removing old sheetrock, they found that a portion of the lower wall was rotting but they were able to correct the issue.
"The bottom portion of the wall was rotted right out about 8 inches from the floor so water coming in from the outside over the years had caused a lot of the wood to rot," he said.
Enzien said although the hangar is anticipated to be largely complete by Christmas, the hangar door installation will likely be complete sometime in the early new year because the contractor must work in tandem with the door manufacturers.
Chairman Jeff Naughton asked that the contractor submit an official request for an extension.
Enzien said not much work has been done on the administrative building project, which is also planned to be renovated, however, the gate improvements are mostly complete.
Enzien said gate eight and gate ten have been motorized and although both gates seem to be functioning, there is a slight issue with the remote-control operation of gate ten. The remote should be able to operate within a 500-foot radius of the gate.
"They don’t know if it is the plantings that are causing a line of sight issue, but I spoke with Berkshire Fence and they are looking at other options," he said. "Hopefully in the next week or so we will have a solution and then we can close out the project."
If you would like to contribute information on this article, contact us at info@iberkshires.com.
Your Comments
iBerkshires.com welcomes critical, respectful dialogue. Name-calling, personal attacks, libel, slander or foul language is not allowed. All comments are reviewed before posting and will be deleted or edited as necessary.
No Comments
Clarksburg Select Board Accepts School Roof Bid, Debates Next Steps
By Tammy Daniels iBerkshires Staff
CLARKSBURG, Mass. — The Select Board last week accepted a bid by D.J. Wooliver & Sons to do the flat roof on the elementary school.
Wooliver was the lowest bid at about $400,000 but cautioned that the cost may rise depending on the conditions once the work started. The work will depend on town meeting approving a borrowing for the project and a possible debt exclusion.
But how much borrow and whether the work will be worth it has been a conundrum for town and school officials. The condition of the school has been a major topic at meetings of the board and the School Committee over the past few months.
Town officials are considering putting the question to the voters — try to piecemeal renovations or begin a new study on renovating or building a new school.
In the meantime, the leaking roof has prompted an array of buckets throughout the school.
"Until they actually get in there and start ripping everything up, we won't really know the extent of all the damage per se so it's really kind of hard to make a decision," board member Colton Andrew said at last week's meeting, broadcast on Northern Berkshire Community Television.
Board member Daniel Haskins wondered if it would be better to patch until a town made a decision on a school project or do a portion of the roof. But Chair Robert Norcross disagreed.
Bailey explained that this change will allow police officers more flexibility when responding to non-emergency calls, reducing wait times at the traffic light and reducing potential traffic congestion when emergency vehicles need to pass through.
click for more
First Congregational Church of North Adams' fourth annual "Share the Love" campaign concluded with over $9,000 raised to support local organizations serving individuals in need. click for more
The School Building Committee's update on Tuesday included that a public records request for the detailed design documents is requiring redaction and review, including by public safety. click for more