image description

Greylock Glen Work Eyed For Thanksgiving Completion

By Andy McKeeveriBerkshires Staff
Print Story | Email Story

Brent White, who is overseeing the construction, detailed what has been done so far and what is left to do with the infrastructure project.
ADAMS, Mass. — The first phase of the infrastructure project at the Greylock Glen is expected to be completed by Thanksgiving, according to the contractor.

Brent White, of White Engineering which is overseeing the construction, said the project is moving along well and workers have not encountered any "surprises."

More than 2,000 feet of sewer line and about 1,100 feet of water line has been laid so far as workers are installing infrastructure up Gould Road.

"We would like to be out of there by Thanksgiving with the possibility of coming back in the spring to do some planting," Dudley Billings, owner of D.R. Billings that was hired for the $2 million construction, told the Greylock Glen Advisory Committee on Thursday.

Work should move down to the intersection of West Road in the next week and the whole road should be paved over by the end of the summer, he said.

The bid for the project as laid out was $1.2 million, below the available $2 million in state funds reserved for the project. With the extra money, Ed Whatley, who designed the project with Vanasse Hangen Brustlin, said they will continue farther up the road than planned.

The second phase of the project, which Director of Community Development Donna Cesan said she hopes will be funded by the state MassWorks program, will finish off the infrastructure. That work will include gas, water and sewer lines as well as electrical poles and a water tank for fire protection at the site.

Cesan said the group is estimating costs to include an event parking area that could be included in the second phase. She said she talked to Massachusetts Museum of Contemporary Art Director Joseph Thompson, who suggested organizing a small concert there if the parking lot was completed.

The infrastructure is the first part of the massive project to develop the 50 acres of land. The full project includes an amphitheater, conference center, camp grounds and hiking trails. The town searched for interest for developers to build the conference center but came up short. They have since switched focus to the campgrounds.


Ed Whatley and Brent White fielded questions from the audience about this project as well as the second phase that the town hopes to complete next year.
Cesan said her department is working on requests for proposals for the campground and for a website designer. The website RFP is expected to be released in the next couple of weeks so the new site can be launched in November or December.

"As you recall, we did not get much in way of response in regards to the lodge and conference center so we are focusing on the campground," Cesan said. "Most of our effort will be focused on our request for proposals."

Cesan said she also found a potential funder to move the project along. Common Capital is a firm that is trying to obtain $50 million in new market tax credits and can match those credits up with a potential builder, she said. The firm has said the town and the project are both eligible for the tax credits so Cesan is applying to Common Capital. The deadline for those applications are at the end of the month.

"This could be 20 to 35 percent of a project," Cesan said.

The committee also talked about invasive species work. Chris Politan of Politan Ecological Services Inc. said a management plan is nearly completed that will guide the invasive species control efforts. Environmental permitting and wetlands issues have bogged down the work but the management plan will put the group on track.

"We've been in a bit of a standstill since the last time I met with you," Politan said.

Tags: Greylock Glen,   invasive species,   

If you would like to contribute information on this article, contact us at info@iberkshires.com.

Historic Yellow Smokestack in Adams Coming Down

By Tammy DanielsiBerkshires Staff

Dust from the brittle bricks blows out from an opening near the base. 
ADAMS, Mass. — The yellow smokestack on Columbia Street is coming down — piece by piece. 
 
Building Commissioner Gerald Garner said the owners of the Berkshire Mill had applied for its demolition after finding serious structural issues with the more than four-story-tall landmark.
 
The stack with its yellow terra cotta tiles, and its slightly shorter red brick companion, are regularly checked for stability. The red one holds antennae for Verizon at its peak but the yellow was not considered structurally stable enough, and was found to have deteriorated at its recent inspection. 
 
Manafort Brothers Inc. of Connecticut started Tuesday on the demolition, pushing the top bricks into the stack from an aerial work platform. The two workers on the platform are using crowbars — and their hands — to topple the bricks. Dust could be seen coming from an opening near the base; dust was also evident in adjacent Walgreens parking lot.
 
Once the stack is about halfway down, and not in danger of falling over, heavy equipment will come in to complete the razing. A worker onsite estimated it will take about a week. 
 
Garner said the town has been apprised of the work and that no toxic elements were found in testing the structure prior to the work. 
 
"I just want it done safely," he said.
 
View Full Story

More Adams Stories