image description

Greylock Glen Work Eyed For Thanksgiving Completion

By Andy McKeeveriBerkshires Staff
Print Story | Email Story

Brent White, who is overseeing the construction, detailed what has been done so far and what is left to do with the infrastructure project.
ADAMS, Mass. — The first phase of the infrastructure project at the Greylock Glen is expected to be completed by Thanksgiving, according to the contractor.

Brent White, of White Engineering which is overseeing the construction, said the project is moving along well and workers have not encountered any "surprises."

More than 2,000 feet of sewer line and about 1,100 feet of water line has been laid so far as workers are installing infrastructure up Gould Road.

"We would like to be out of there by Thanksgiving with the possibility of coming back in the spring to do some planting," Dudley Billings, owner of D.R. Billings that was hired for the $2 million construction, told the Greylock Glen Advisory Committee on Thursday.

Work should move down to the intersection of West Road in the next week and the whole road should be paved over by the end of the summer, he said.

The bid for the project as laid out was $1.2 million, below the available $2 million in state funds reserved for the project. With the extra money, Ed Whatley, who designed the project with Vanasse Hangen Brustlin, said they will continue farther up the road than planned.

The second phase of the project, which Director of Community Development Donna Cesan said she hopes will be funded by the state MassWorks program, will finish off the infrastructure. That work will include gas, water and sewer lines as well as electrical poles and a water tank for fire protection at the site.

Cesan said the group is estimating costs to include an event parking area that could be included in the second phase. She said she talked to Massachusetts Museum of Contemporary Art Director Joseph Thompson, who suggested organizing a small concert there if the parking lot was completed.

The infrastructure is the first part of the massive project to develop the 50 acres of land. The full project includes an amphitheater, conference center, camp grounds and hiking trails. The town searched for interest for developers to build the conference center but came up short. They have since switched focus to the campgrounds.


Ed Whatley and Brent White fielded questions from the audience about this project as well as the second phase that the town hopes to complete next year.
Cesan said her department is working on requests for proposals for the campground and for a website designer. The website RFP is expected to be released in the next couple of weeks so the new site can be launched in November or December.

"As you recall, we did not get much in way of response in regards to the lodge and conference center so we are focusing on the campground," Cesan said. "Most of our effort will be focused on our request for proposals."

Cesan said she also found a potential funder to move the project along. Common Capital is a firm that is trying to obtain $50 million in new market tax credits and can match those credits up with a potential builder, she said. The firm has said the town and the project are both eligible for the tax credits so Cesan is applying to Common Capital. The deadline for those applications are at the end of the month.

"This could be 20 to 35 percent of a project," Cesan said.

The committee also talked about invasive species work. Chris Politan of Politan Ecological Services Inc. said a management plan is nearly completed that will guide the invasive species control efforts. Environmental permitting and wetlands issues have bogged down the work but the management plan will put the group on track.

"We've been in a bit of a standstill since the last time I met with you," Politan said.

Tags: Greylock Glen,   invasive species,   

If you would like to contribute information on this article, contact us at info@iberkshires.com.

Greylock 14U Softball Team Tops Dalton

By Stephen DravisiBerkshires.com Sports
NORTH ADAMS, Mass. – The Greylock Thunder 14-and-under travel softball team Saturday ended pool play in its Summer Storm Tournament just like it began pool play on Friday: with a win over Berkshire County rival.
 
Genevieve Lagess went 2-for-2 with a pair of triples and scored three times, and the Thunder overcame an early deficit to take a 13-9 win over Dalton in the pool play finale on Francis Millard Field.
 
On Sunday morning, the eight teams in the tournament will be seeded for the 10 a.m. quarter-final round.
 
The four survivors move on to a pair of 1:30 p.m. semi-finals with the title game scheduled for about 3:30 p.m.
 
The Thunder, which beat the Berkshire Force on Friday night, started its Saturday with an 8-3 loss to the South Troy Dodgers.
 
Then it started its third game of the tournament with a 3-0 lead after Lagess tripled and scored on a wild pitch in the first and Marlee Arnhold and Sadie Stuebner scored in the second.
 
But Dalton battled back in the bottom of the second.
 
View Full Story

More Adams Stories